Operations & Supply Chain · Operations Management

Ops Under Pressure — Empaques del Trópico

A four-round, advanced operations and supply-chain simulation set inside Empaques del Trópico S.A., a Costa Rican sustainable-packaging manufacturer (USD 86M revenue, ~13% EBITDA margin ≈ USD 11.2M, 3 lines / 2 shifts at 78% utilization, 55% of revenue tied to a volatile agricultural-export calendar).

4 rounds Executive English, Español

Preview

About this simulation

A four-round, advanced operations and supply-chain simulation set inside Empaques del Trópico S.A., a Costa Rican sustainable-packaging manufacturer (USD 86M revenue, ~13% EBITDA margin ≈ USD 11.2M, 3 lines / 2 shifts at 78% utilization, 55% of revenue tied to a volatile agricultural-export calendar).

A demand whipsaw — a +38% January surge, on-time delivery collapsing to 81% vs a 96% target, USD 240,000 in late-delivery penalties, then USD 3.1M of excess inventory (≈52 days vs a 30-day target) from a panic overcorrection — collides with a static spreadsheet plan, a single-sourced compostable-resin supplier (6-week lead time, 3-week delay flagged), and a USD 14M two-year contract that demands +20% capacity.

Playing the new operations manager with a USD 6M modernization budget and two quarters to deliver, you (1) diagnose the system, not the symptom — separating true external volatility from self-inflicted variability and naming the root cause behind the bullwhip / overcorrection loop; (2) set capacity under volatile demand — go/no-go on the USD 14M contract and the permanent-versus-flexible capacity mix, sized to a demand distribution and a service level rather than last month's headline; (3) choose the digitalization investment — allocating the digital slice across demand-sensing/S&OP, MES + line sensors, an automated warehouse, or a supplier control tower, recognising that information-centric Industry 4.0 tools often beat throughput-centric ones for a volatility problem; and (4) redesign inventory buffers and defend the integrated operating plan — statistical, item-differentiated safety stock toward the 30-day target, a response to the single-sourced resin risk, and a KPI scorecard.

Grounded in Roy Zúñiga's (INCAE) behavioral-operations and system-dynamics research, the math rewards damping the bullwhip, flexible capacity, information-first digital spend and risk-differentiated buffers — and punishes the five classic errors: a recency-driven permanent-capacity bet, over-producing into the glut, signing the contract before fixing variability, buying throughput when the constraint is decision quality, and a flat safety-stock policy that ignores the upstream supply risk.

Final KPIs track On-Time Delivery, Inventory days, Capacity Utilization and the cumulative cost/P&L impact in USD.

Who it is for

An advanced simulation for participants used to working with the main frameworks and trade-offs of the subject, designed for executive education and experienced professionals.

How a session runs

  1. The instructor creates a session from the Eureka dashboard and invites the participants.
  2. Participants play 4 rounds. In each one they submit their decisions and the simulation calculates the results.
  3. The simulation can be run in English, Español.
  4. The instructor follows each participant's progress and results from the dashboard, and uses the class results for the debrief.

Decisions participants make

The decisions participants make during the simulation:

  • What is the ROOT cause behind the missed quarter — the lever that addresses the cause, not the symptom?
  • How much of the chaos is SELF-INFLICTED variability vs true external demand swing? (% self-inflicted)
  • Name the feedback loop you most need to break.
  • The USD 14M / 2-year contract requires +20% capacity and tighter service. Go or no-go?
  • How do you source the capacity to handle peaks? (% from PERMANENT new line/shift vs flexible)
  • Size capacity to a point forecast, or to a demand DISTRIBUTION and a chosen service level?
  • Allocate the digitalization slice of the budget across the four investments (must total $3.0M)
  • What decision process does the technology actually enable?
  • Redesign safety stock toward the 30-day target. Flat policy, or item-differentiated?
  • Response to the single-sourced compostable-resin risk (6-week lead time, 3-week delay flagged).

What participants track

What participants follow on screen as the rounds go by:

  • OTD, Inventory & Utilization Trajectory

Subjects covered

Designed for courses in Operations Management.